Chapter 15 Construction Scheduling 265
11. True or False? Money in a job account is available to all managers on a
job site.
12. Permits are
______.
A. written documents that grant a company permission to build,
remodel, or repair a structure
B. obtained by the general contractor
C. granted by the local governmental body
D. All of the above.
Activities
1. Imagine that you are going to install a basketball hoop. The pole will
be placed in a hole in the ground that will be filled with concrete. The
rim and backboard cannot be attached to the pole until the concrete has
cured for five days. Prepare a bar chart for the project. Omit the cost and
percentage of job data from your chart.
2. Prepare a critical path method network for the basketball hoop project
described in Activity 1.
3. Prepare a list of tools needed to complete each activity identified in
either the bar chart from Activity 1 above, or the critical path network
from Activity 2 above.